Network Reinforcement: City Centre and South Belfast, 2024

Road Reinforcement 2024

Phoenix Energy are carrying out essential planned reinforcement of our network in Belfast city centre and South Belfast. This is to ensure that we continue to meet the needs of our growing and existing customer base now, and into the future.   

Work is scheduled to continue until the end of August 2024.  

We encourage you to keep up to date with progress and upcoming areas of work via this page to best inform your travel arrangements in this area, as timescales are subject to change.    

Works Update 21.11.24

Construction is planned to take place between Dromara Street and Balfour Avenue as part of the Centre and South Belfast Network Reinforcement Project. 

The work is scheduled to commence on Tuesday 3rd December and provisionally end on Friday 20th December 2024. It will be completed along the grass verge with some work taking place on Saturdays to help minimise the duration of the programme.

Please download the map to view the area of works.

Works Update 08.11.24

Phoenix Energy will be working on the two citybound lanes of the Ormeau Road at Dromara Street on Saturday 9th November to complete pipe laying across the road. 

The two citybound lanes will be taken out, but traffic heading towards the city and towards the country will be able to flow due to our traffic management. 

Traffic will be reduced to one lane in both directions through the site. Works are anticipated to last until early afternoon only. There will be no Sunday working due to Remembrance Sunday.

Please download the map to view the area of works.

Phoenix Reinforcement city centre and South Belfast Phasing

We have, and will continue to, engage with the Department for Infrastructure, public representatives, and members of the public to identify opportunities to continue minimising the impact on journey times.  

We would like to thank you for your patience and understanding during these essential planned works.

Please note, all timescales are subject to change

Belfast Reinforcement City Centre Phasing Jpg

Phoenix Reinforcement city centre and South Belfast Phasing

To download maps and information on both road and lane closures of our Phases 1 - 4 of our works, please click the Download Now button. 

Please note, all timescales are subject to change.

Download Now

Phase 1

1.1) Alfred Street - Road Closure, 7th - 16th May - COMPLETED

1.2) Hamilton Street - Road Closure 17th - 26th May - COMPLETED

Phase 1 of this project is now complete. 

We will be carrying out road reinforcement in this area on 28th June

Phase 2

2.1) Dromara Street 27th May – 2nd June - COMPLETED

2.2) Balfour Avenue to Hatfield Street, Road Closure, 3rd – 9th June - COMPLETED

2.3) Balfour Ave (Hatfield to Cooke), Road Closure, 10th - 16th June - COMPLETED

2.4) Cooke Street, Road Closure, 17th - 27th June - COMPLETED

2.5) Ormeau Crossing, Lane Closure, 21st - 23rd June - COMPLETED

Phase 3

3.1) Donegall Quay to Oxford Street, Lane Closure, 24th June - 14th July COMPLETED

3.2) Queens Bridge, Lane Closure, 28th - 20th July - COMPLETED

3.3) Lanyon PLace Crossroads, Lane Closure, 20th - 21st July - COMPLETED

3.4) East Bridge Street, Lane Closure, 15th - 28th July - COMPLETED

3.5) East Bridge Street Crossing, Lane Closure, 27th - 28th July - COMPLETED

3.6) Cromac Street Crossing, Lane Closure, 25th - 28th July - COMPLETED

Phase 4

4.1) Ormeau Rd (Cooke Street to Ormeau Avenue), Lane Closure, 29th July - 18th August - COMPLETED

4.2) Ormeau Bridge, Lane Closure, 1st August - 4th August - COMPLETED

4.3) Gasworks Crossroads, Lane Closure and Road Closure, 10th - 11th August - COMPLETED

4.4) Ormeau Ave, One Way Closure, 19th - 25th August