Network Reinforcement: Upper Newtownards Road, 2024/25

Network Reinforcement 2024/25

Phoenix Energy are carrying out essential planned reinforcement of our network on the Upper Newtownards Road. This is to ensure that we continue to meet the needs of our growing and existing customer base now, and into the future.   

This project started on 26th August 2024 and is scheduled to continue until the end of April 2025.

We encourage you to keep up to date with progress and upcoming areas of work via this page to best inform your travel arrangements in this area, as timescales are subject to change.

Latest Update: 23rd September

We are pleased to report that Phase 1 of this project is now due to be completed ahead of schedule, which allows us to commence the next phase of the programme on Monday 30th September 2024. As a result of the early completion of Phase 1 we now plan to move to Phase 3 of the programme.  

This next phase of works will start at the Comber Road junction, moving country bound to the Ballyregan Road, scheduled for a 4-week period (Monday 30th September to 25th October 2024).  

Once completed, we plan to move to Phase 2 of the project (Ballyregan Road to Dunlady Road, going through Dundonald Village), scheduled for Saturday 26th October to Friday 8th November.

Upper Newtownards Road Works Jpg

We have, and will continue to, engage with the Department for Infrastructure, public representatives, and members of the public to identify opportunities to continue minimising the impact on journey times.   

We would like to thank you for your patience and understanding during these essential planned works.   

Phoenix Reinforcement Upper Newtownards Road Phasing

Please note all timescales subject to change.

Phase 1 - Active

- Carrowreagh Road to Dunlady Road.

- From Monday 26th August to Sunday 13th October (now scheduled to complete by Monday 30th September).  

- Saturday 21st and Sunday 22nd September - works taking place at Dunlady Road/Robbs Road junction .  

-Local diversions are in place.


Phase 3 - Scheduled

- Comber Road to Ballyregan Road.  

- From Monday 30th September to Friday 25th October.  

- The two central lanes of traffic will be closed, allowing traffic to flow via one lane, in both directions.  

- Local diversions will be in place for side streets.


Phase 2 - Scheduled

- Ballyregan Road to Dunlady Road.  

- From Saturday 26th October to Friday 8th November.  

- The two central lanes of traffic will be closed, allowing traffic to flow via one lane, in both directions.  

- Local diversions will be in place for side streets.


Phase 4 - Scheduled

- Comber Road to Hawthornden Way.  

- From November 2024 to April 2025.  

- The two central lanes of traffic will be closed, allowing traffic to flow via one lane, in both directions.  

- Works will not take place over the month of December.  

- Local diversions will be in place for side streets.