Network Reinforcement: Upper Newtownards Road, 2024/25

Network Reinforcement 2024/25

Phoenix Energy are carrying out essential planned reinforcement of our network on the Upper Newtownards Road. This is to ensure that we continue to meet the needs of our growing and existing customer base now, and into the future.   

This project started on 26th August 2024 and is scheduled to continue until the end of April 2025.

We encourage you to keep up to date with progress and upcoming areas of work via this page to best inform your travel arrangements in this area, as timescales are subject to change.

Upper Newtownards Road Works Jpg

We have, and will continue to, engage with the Department for Infrastructure, public representatives, and members of the public to identify opportunities to continue minimising the impact on journey times.   

We would like to thank you for your patience and understanding during these essential planned works.   

Latest Update: 13th December 2024

Gas works are currently paused for the festive season as the embargo continues until early January 2025. The final phase of works will start at the Stoney Road junction on Monday 6th January 2025, moving citybound to Hawthornden Way. 

Two central lanes will be closed as work takes place, allowing traffic to flow via one lane in a citybound and country bound direction. The works are scheduled for approximately 16 weeks, ending April 2025. 

Local diversions will be in place for side streets and all work will be carried out in small sections to minimise impact to commuters.

Please download the map below to view the area of works:

Stoney Road to Hawthornden Way works map (pdf)

Latest Update: 11th November 2024

Phases 1 to 3 are now complete which allows us to move onto Phase 4, starting at Dundonald Cemetery, and moving citybound to the Rosepark junction, scheduled for a 2-week period starting Monday 11th November until Sunday 24th November.

Two central lanes will be closed as work takes place, allowing traffic to flow via one lane in a citybound and country bound direction.

There will be an embargo on all roadworks from Monday 25th November until the beginning of January which means there will not be any disruption to commuters and Christmas shoppers throughout December.

Please download the map below to view the area of works:

Rosepark works map (pdf)

Schedule of Works

Phase 4 - Active

- Monday 6th January 2025 to April 2025 - works planned to take place at the Stoney Road junction, moving city bound to Hawthornden Way. Two central lanes will be closed as work takes place, allowing traffic to flow via one lane in a citybound and country bound direction. Local diversions will be in place for side streets.

- There will be an embargo on all roadworks from Monday 25th November until the beginning of January which means there will not be any disruption to commuters and Christmas shoppers throughout December.

- Monday 11th November to Sunday 24th November: Works taking place at Dundonald Cemetery, moving citybound to the Rosepark junction are now complete.

Phase 2 - Complete

- Ballyregan Road to Dunlady Road.  

- From Saturday 26th October to Friday 8th November.  

- Saturday 26th and Sunday 27th October: works taking place at Ballyregan Road junction are now complete.

Phase 3 - Complete

- Comber Road to Ballyregan Road.  

- From Monday 30th September to Friday 25th October.  

- Saturday 5th and Sunday 6th October – works taking place at Comber Road junction are now complete.

- Saturday 19th and Sunday 20th October - works taking place at East Link Road junction are now complete.

Phase 1 - Complete

- Carrowreagh Road to Dunlady Road.

- From Monday 26th August to Sunday 13th October (now scheduled to complete by Monday 30th September).  

- Saturday 21st and Sunday 22nd September - works taking place at Dunlady Road/Robbs Road junction are now complete.  

Please note all timescales subject to change. Last updated Friday 13th December.